To set up a factory in Saudi Arabia you need (1) a company: MISA investment registration if foreign-owned, then a CR. (2) A site: land or a ready-built factory in a MODON industrial city, or in Jubail/Yanbu (Royal Commission) or a Special Economic Zone. (3) The industrial licence from the Ministry of Industry and Mineral Resources (MIM). Its initial stage is issued online (about 48 hours), is valid for one year and does not allow production; the final production stage comes after the factory is built and inspected. (4) Environmental, civil defence and building permits. Expect about 4–9 months for a new-build factory, less with a ready-built unit.
Talk to our team in Al Jubail on WhatsApp or call +966 54 961 1338. Arabic and English.
Factory setup in 60 seconds
| Question | Answer |
|---|---|
| Who issues the industrial licence? | Ministry of Industry and Mineral Resources (MIM), via the Industrial Platform |
| What does MODON do? | Provides industrial land, ready-built factories and services in MODON industrial cities, plus permits inside its cities |
| Foreign ownership | Up to 100% in most manufacturing activities, with MISA investment registration |
| Initial industrial licence | Online, about 48 hours, valid 1 year, no production allowed |
| Production | Allowed only at the final (production) stage of the industrial licence |
| Other permits | Environmental (NCEC), Civil Defense, building permit, utilities, sector approvals (SFDA, SASO) |
| Timeline | About 4–9 months new-build; faster with a ready-built factory |
| Financing | Saudi Industrial Development Fund (SIDF) loans for eligible projects |
MODON licence vs. industrial licence: clearing the confusion
Many guides talk about a “MODON licence”. In practice there are two different things:
| Industrial licence | MODON contract and permits | |
|---|---|---|
| Issued by | MIM (Ministry of Industry and Mineral Resources) | MODON (Saudi Authority for Industrial Cities and Technology Zones) |
| What it gives | Permission to establish and later operate an industrial project | Land lease or ready-built factory, plus building and operating services in the city |
| Needed if you build outside MODON? | Yes | No: you use RCJY, an SEZ or another approved site |
You usually apply for the MODON site and the MIM licence in parallel, because the licence application asks for your site details.
Where to build your factory
| Location | Run by | Best for |
|---|---|---|
| MODON industrial cities (Riyadh, Jeddah, Dammam, Sudair, Qassim, Madinah and many more) | MODON | Most light and medium manufacturing; ready-built factories available |
| Jubail and Yanbu Industrial Cities | Royal Commission for Jubail and Yanbu | Petrochemicals, heavy industry, downstream chemicals (RCJY guide) |
| Special Economic Zones (e.g. Ras Al-Khair, Jazan, KAEC) | Economic Cities and Special Zones Authority | Export-oriented projects needing special incentives |
Step-by-step factory setup process
- Feasibility and activity check: confirm your ISIC manufacturing activity, products, capacity, site needs and any sector regulator (SFDA, SASO, Ministry of Energy for fuel or feedstock).
- Company set-up: MISA investment registration for foreign investors, then the CR through the Saudi Business Center.
- Choose and book the site: apply to MODON for land or a ready-built factory (or RCJY/SEZ), and sign the lease.
- Industrial licence, initial stage: apply on MIM’s Industrial Platform. The initial licence is valid for one year and lets you complete the project requirements, but not produce.
- Design and permits: building permit, environmental permit from the National Center for Environmental Compliance, Civil Defense approvals, utility connections.
- Build or fit out the factory and install machinery (consider customs duty exemptions on machinery and raw materials available to licensed industrial projects).
- Hire and register staff: GOSI, Qiwa, Muqeem, Mudad and Saudization targets (Qiwa guide).
- Inspection and production stage: complete the final stage of the industrial licence, which authorises actual production.
- Product compliance: SABER/SASO conformity for regulated products, SFDA for food, cosmetics and pharma, ZATCA e-invoicing (LUBA ERP).
- Sell: register as a supplier with Aramco, SABIC, Ma’aden, NEOM and government buyers. Local manufacturers often get local content preference (vendor registration guides).
Factory setup costs: what you pay for
Costs depend on city, size, sector and whether you build or rent. These are the cost items to budget:
| Cost item | Paid to | Notes |
|---|---|---|
| MISA registration and CR | MISA, Ministry of Commerce | Shown on the portals when you apply |
| Industrial licence | MIM | Online application |
| Land lease or ready-built factory rent | MODON / RCJY / SEZ | Yearly, per square metre; varies by city and infrastructure |
| Design and construction | Contractors | The largest cost for a new-build |
| Utilities connection | Power, water, gas providers | Depends on load and location |
| Environmental and Civil Defense permits | NCEC, Civil Defense | Plus consultant studies (EIA) |
| Machinery and installation | Suppliers | Check customs exemptions |
| Staff, iqamas, GOSI | Government platforms | Saudization targets apply |
| Working capital | — | Raw materials, 3–6 months of operations |
MODON publishes land and factory offers on its platform, so ask for a site-specific quote before you finalise your feasibility study. Many published “average” figures online are rough and out of date.
Incentives for manufacturers
- SIDF financing for eligible industrial projects
- Customs duty exemptions on machinery, spare parts and raw materials for licensed industrial projects (apply through MIM)
- Ready-built factories in MODON cities to save time
- Local content preference in government procurement and with Aramco (IKTVA)
- Special Economic Zone incentives for qualifying projects
Timeline
| Stage | Typical time |
|---|---|
| MISA registration and CR | 1–3 weeks |
| MODON site allocation and lease | Weeks, depending on availability |
| Initial industrial licence | About 48 hours once the application is complete |
| Design, permits and construction | 3–6+ months (new-build) |
| Production stage approval | After inspection |
| Total | About 4–9 months new-build; shorter with a ready-built factory |
Common mistakes
- Thinking the initial industrial licence allows production (it doesn’t)
- Signing a site lease before checking utilities and environmental constraints
- Ignoring SASO/SFDA product approvals until after production starts
- Under-budgeting Saudization and iqama costs
- Not registering as a supplier early, so the factory is ready but has no buyers
How Luba helps
From Al Jubail, the heart of Saudi industry, we handle the whole path: MISA and CR, MODON or Royal Commission site applications, the MIM industrial licence, permits coordination, GOSI, Qiwa and Muqeem, ZATCA e-invoicing with LUBA ERP, ISO certification and vendor registration with Aramco (including 9COM approval), SABIC and Ma’aden. See our company formation service.
Sources
- Ministry of Industry and Mineral Resources – Issuance of Industrial License
- Saudi Press Agency – Upgraded version of the industrial license
- MODON – official website
- SABIC Nusaned – Industrial Cities and Technology Zones (MODON)
Talk to our team in Al Jubail on WhatsApp or call +966 54 961 1338. Arabic and English.
Frequently asked questions
How do I set up a factory in Saudi Arabia?
Set up the company (MISA registration if foreign, then CR), secure a site from MODON, the Royal Commission or a Special Economic Zone, get the MIM industrial licence, obtain environmental, civil defence and building permits, build and equip the factory, then complete the licence’s production stage.
Who issues the industrial licence in Saudi Arabia?
The Ministry of Industry and Mineral Resources (MIM), through its Industrial Platform.
What is MODON?
The Saudi Authority for Industrial Cities and Technology Zones. It develops industrial cities and provides industrial land, ready-built factories and services.
Can I start production with the initial industrial licence?
No. MIM says the initial licence is valid for one year and lets you complete project requirements but does not entitle you to start production. Production is allowed at the licence’s final stage.
Can a foreigner own 100% of a factory in Saudi Arabia?
Yes, in most manufacturing activities, after registering with MISA under the Investment Law.
How long does it take to set up a factory?
About 4–9 months for a new-build factory, depending on permits and construction; a ready-built MODON factory can be much faster.
How much does it cost to set up a factory in Saudi Arabia?
It depends on city, size and sector. Main items are land or factory rent, construction, utilities, machinery, permits, staff and working capital. Get a site-specific MODON quote for your feasibility study.
Does MODON offer ready-built factories?
Yes. MODON offers ready-built factory units in its industrial cities, which shortens setup time.
Where should a petrochemical factory be located?
Usually in Jubail or Yanbu Industrial Cities (Royal Commission), close to feedstock and petrochemical customers.
Can Luba help with factory setup?
Yes. We handle company setup, MODON or RCJY site applications, the industrial licence, government registrations, ISO, ZATCA and vendor registration with major buyers.