Factory Setup in Saudi Arabia (2026): MODON, Industrial Licence, Costs and Step-by-Step Process

How to set up a factory in Saudi Arabia: MISA, CR, MODON land or ready-built factory, MIM industrial licence stages, permits, costs, incentives, timeline and FAQs.

Quick answer

To set up a factory in Saudi Arabia you need (1) a company: MISA investment registration if foreign-owned, then a CR. (2) A site: land or a ready-built factory in a MODON industrial city, or in Jubail/Yanbu (Royal Commission) or a Special Economic Zone. (3) The industrial licence from the Ministry of Industry and Mineral Resources (MIM). Its initial stage is issued online (about 48 hours), is valid for one year and does not allow production; the final production stage comes after the factory is built and inspected. (4) Environmental, civil defence and building permits. Expect about 4–9 months for a new-build factory, less with a ready-built unit.

Need help with factory setup in Saudi Arabia?

Talk to our team in Al Jubail on WhatsApp or call +966 54 961 1338. Arabic and English.

Factory setup in 60 seconds

QuestionAnswer
Who issues the industrial licence?Ministry of Industry and Mineral Resources (MIM), via the Industrial Platform
What does MODON do?Provides industrial land, ready-built factories and services in MODON industrial cities, plus permits inside its cities
Foreign ownershipUp to 100% in most manufacturing activities, with MISA investment registration
Initial industrial licenceOnline, about 48 hours, valid 1 year, no production allowed
ProductionAllowed only at the final (production) stage of the industrial licence
Other permitsEnvironmental (NCEC), Civil Defense, building permit, utilities, sector approvals (SFDA, SASO)
TimelineAbout 4–9 months new-build; faster with a ready-built factory
FinancingSaudi Industrial Development Fund (SIDF) loans for eligible projects

MODON licence vs. industrial licence: clearing the confusion

Many guides talk about a “MODON licence”. In practice there are two different things:

Industrial licenceMODON contract and permits
Issued byMIM (Ministry of Industry and Mineral Resources)MODON (Saudi Authority for Industrial Cities and Technology Zones)
What it givesPermission to establish and later operate an industrial projectLand lease or ready-built factory, plus building and operating services in the city
Needed if you build outside MODON?YesNo: you use RCJY, an SEZ or another approved site

You usually apply for the MODON site and the MIM licence in parallel, because the licence application asks for your site details.

Where to build your factory

LocationRun byBest for
MODON industrial cities (Riyadh, Jeddah, Dammam, Sudair, Qassim, Madinah and many more)MODONMost light and medium manufacturing; ready-built factories available
Jubail and Yanbu Industrial CitiesRoyal Commission for Jubail and YanbuPetrochemicals, heavy industry, downstream chemicals (RCJY guide)
Special Economic Zones (e.g. Ras Al-Khair, Jazan, KAEC)Economic Cities and Special Zones AuthorityExport-oriented projects needing special incentives

Step-by-step factory setup process

  1. Feasibility and activity check: confirm your ISIC manufacturing activity, products, capacity, site needs and any sector regulator (SFDA, SASO, Ministry of Energy for fuel or feedstock).
  2. Company set-up: MISA investment registration for foreign investors, then the CR through the Saudi Business Center.
  3. Choose and book the site: apply to MODON for land or a ready-built factory (or RCJY/SEZ), and sign the lease.
  4. Industrial licence, initial stage: apply on MIM’s Industrial Platform. The initial licence is valid for one year and lets you complete the project requirements, but not produce.
  5. Design and permits: building permit, environmental permit from the National Center for Environmental Compliance, Civil Defense approvals, utility connections.
  6. Build or fit out the factory and install machinery (consider customs duty exemptions on machinery and raw materials available to licensed industrial projects).
  7. Hire and register staff: GOSI, Qiwa, Muqeem, Mudad and Saudization targets (Qiwa guide).
  8. Inspection and production stage: complete the final stage of the industrial licence, which authorises actual production.
  9. Product compliance: SABER/SASO conformity for regulated products, SFDA for food, cosmetics and pharma, ZATCA e-invoicing (LUBA ERP).
  10. Sell: register as a supplier with Aramco, SABIC, Ma’aden, NEOM and government buyers. Local manufacturers often get local content preference (vendor registration guides).

Factory setup costs: what you pay for

Costs depend on city, size, sector and whether you build or rent. These are the cost items to budget:

Cost itemPaid toNotes
MISA registration and CRMISA, Ministry of CommerceShown on the portals when you apply
Industrial licenceMIMOnline application
Land lease or ready-built factory rentMODON / RCJY / SEZYearly, per square metre; varies by city and infrastructure
Design and constructionContractorsThe largest cost for a new-build
Utilities connectionPower, water, gas providersDepends on load and location
Environmental and Civil Defense permitsNCEC, Civil DefensePlus consultant studies (EIA)
Machinery and installationSuppliersCheck customs exemptions
Staff, iqamas, GOSIGovernment platformsSaudization targets apply
Working capital—Raw materials, 3–6 months of operations

MODON publishes land and factory offers on its platform, so ask for a site-specific quote before you finalise your feasibility study. Many published “average” figures online are rough and out of date.

Incentives for manufacturers

  • SIDF financing for eligible industrial projects
  • Customs duty exemptions on machinery, spare parts and raw materials for licensed industrial projects (apply through MIM)
  • Ready-built factories in MODON cities to save time
  • Local content preference in government procurement and with Aramco (IKTVA)
  • Special Economic Zone incentives for qualifying projects

Timeline

StageTypical time
MISA registration and CR1–3 weeks
MODON site allocation and leaseWeeks, depending on availability
Initial industrial licenceAbout 48 hours once the application is complete
Design, permits and construction3–6+ months (new-build)
Production stage approvalAfter inspection
TotalAbout 4–9 months new-build; shorter with a ready-built factory

Common mistakes

  • Thinking the initial industrial licence allows production (it doesn’t)
  • Signing a site lease before checking utilities and environmental constraints
  • Ignoring SASO/SFDA product approvals until after production starts
  • Under-budgeting Saudization and iqama costs
  • Not registering as a supplier early, so the factory is ready but has no buyers

How Luba helps

From Al Jubail, the heart of Saudi industry, we handle the whole path: MISA and CR, MODON or Royal Commission site applications, the MIM industrial licence, permits coordination, GOSI, Qiwa and Muqeem, ZATCA e-invoicing with LUBA ERP, ISO certification and vendor registration with Aramco (including 9COM approval), SABIC and Ma’aden. See our company formation service.

Sources

Need help with factory setup in Saudi Arabia?

Talk to our team in Al Jubail on WhatsApp or call +966 54 961 1338. Arabic and English.

Frequently asked questions

How do I set up a factory in Saudi Arabia?

Set up the company (MISA registration if foreign, then CR), secure a site from MODON, the Royal Commission or a Special Economic Zone, get the MIM industrial licence, obtain environmental, civil defence and building permits, build and equip the factory, then complete the licence’s production stage.

Who issues the industrial licence in Saudi Arabia?

The Ministry of Industry and Mineral Resources (MIM), through its Industrial Platform.

What is MODON?

The Saudi Authority for Industrial Cities and Technology Zones. It develops industrial cities and provides industrial land, ready-built factories and services.

Can I start production with the initial industrial licence?

No. MIM says the initial licence is valid for one year and lets you complete project requirements but does not entitle you to start production. Production is allowed at the licence’s final stage.

Can a foreigner own 100% of a factory in Saudi Arabia?

Yes, in most manufacturing activities, after registering with MISA under the Investment Law.

How long does it take to set up a factory?

About 4–9 months for a new-build factory, depending on permits and construction; a ready-built MODON factory can be much faster.

How much does it cost to set up a factory in Saudi Arabia?

It depends on city, size and sector. Main items are land or factory rent, construction, utilities, machinery, permits, staff and working capital. Get a site-specific MODON quote for your feasibility study.

Does MODON offer ready-built factories?

Yes. MODON offers ready-built factory units in its industrial cities, which shortens setup time.

Where should a petrochemical factory be located?

Usually in Jubail or Yanbu Industrial Cities (Royal Commission), close to feedstock and petrochemical customers.

Can Luba help with factory setup?

Yes. We handle company setup, MODON or RCJY site applications, the industrial licence, government registrations, ISO, ZATCA and vendor registration with major buyers.

Written by the Luba Global Ventures LLC team

Practitioners in Saudi vendor registration, company formation and compliance, based in Al Jubail. Reviewed . Ask us a question.

Need it done for you?

Discuss Your Saudi Business Setup Requirements

Every company formation case is different. Tell us about your business activity, ownership structure and objectives, and we’ll help you identify the relevant requirements and next steps.